The Ontario Land Tribunal has approved a draft plan of subdivision agreement between the City of Hamilton and the owners of 9451, 9517, 9569, 9579, 9593 & 9867 Dickenson Road and 1199 & 1205 Glancaster Road.
The industrial-zoned lands are directly adjacent to the runway on the north side of the airport.
The developer sought permissions to construct four development blocks totalling approximately 76.6 hectares of development area with permissions to accommodate a gross floor area of approximately 295,326 square metres of employment uses.
Similar to many other projects in the area of Hamilton’s airport, one of the primary issues for the City is the allocation of capacity in the new trunk sewer into the area.
In a written hearing, the OLT states it has approved a settlement that permits the development.
Here’s the technical summary:
Special Conditions for Draft Plan of Subdivision Approval for 25T-202203
That this approval for the Draft Plan of Subdivision, 25T-202203, prepared by Landwise, and certified by Thomas J. Salb, O.L.S., dated July 10, 2025, consisting of:
- Phase 1: three blocks for employment uses (Blocks 1, 2 and 5), three blocks for road widening (Blocks 6, 7, and 8), four natural heritage system (NHS) blocks (Blocks 9, 10, 13, and 18), two stormwater management blocks (Blocks 11 and 12), one reserve block for future development (Block 15), two NHS watercourse channel blocks (Blocks 16 and 17), two overland drainage blocks (Blocks 21 and 22), four NHS watercourse channel buffer blocks (Blocks 23, 24, 25, and 26), four NHS buffer blocks (Blocks 27, 28, 29, and 30)
- Phase 2: two blocks for employment uses (Blocks 3 and 4), two temporary road right-of-way blocks (Blocks 19 and 20), one stormwater management block (Block 14), and the remainder of the public road.
Paragraphs 30 to 39 of the agreement deal with sanitary sewer and watermain construction and connections. In sum, the development group will be required to bear their share of costs for extensions to the property. Other developments in the area will bear their share of costs.
The decision is expected to be posted to CanLII in the coming days.