Hamilton’s General Manager of Public Works says the City meeting with Ministry of Labour officials on Wednesday was productive.

The meeting followed the City’s attempting to do work related to the site on TuesdayGM Carlyle Khan says moving forward the City “is going to make sure [the Ministry] knows every single that we do in the vicinity of the site.”

Last week, the Ministry issued a series of stop-work orders against the City.

On Tuesday, a City electrical contractor was working at an intersection of the property, prompting a Ministry visit. The work was paused.

Electrical contractors, hired by the City of Hamilton, working beside the Barton and Tiffany lands during the morning of November 26, 2024

Khan says the City is installing a pedestrian crossover light on Barton Street at Caroline Street. Tuesday’s work to install the light occurred within the right of way of traffic operations.

The City will have a general contractor in place next week.

“They’re going to take it over, and take the role of constructor,” Khan says. “They will coordinate all that and keep us informed.”

“We’re going to communicate to the public as we move forward.”

Khan says the traffic signal installation will resume once the general contractor is in place.

A Ministry of Labour official meeting with City of Hamilton staff at the Barton and Tiffany site on November 27, 2024 Credit: Joey Coleman

Production Details
v. 1.0.0
Published: November 28, 2024
Last updated: November 28, 2024
Author: Joey Coleman
Update Record
v. 1.0.0 original version

Leave a comment

Your email address will not be published. Required fields are marked *